Question No 10:
A major theme park is expanding the existing facility over a five-year period. The design
phase will be completed one year after the contract is awarded. Major engineering
drawings will be finalized two years after the design contract is awarded and construction
will begin three years after the award of the design contract. New, unique ride technology
will be used and an estimate will need to be developed to identify these costs that have no
historical data.
In an exit interview, an employee comments that the reason he is leaving the organization
is lack of teamwork and cohesion among his co-workers. Which need of Maslow's
hierarchy of needs is unmet?
A. Belongingness needs
B. Primary needs
C. Self-actualization needs
D. Esteem needs
Answer: A
Friday, 20 November 2015
Friday, 13 November 2015
Certified Cost Professional Question No 9
Question No 9:
The process of stating goals and determining the most effective way of reaching them isthe definition for:
A. Implementing
B. Mission Statement
C. Managing
D. Planning
Answer: D
Thursday, 5 November 2015
Certified Cost Professional Question No 8
Question No 8:
A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be
installed. How many cubic yards of concrete will be required?
A. 3.0 cubic yards
B. 2.0 cubic yards
C. 3.5 cubic yards
D. 2.5 cubic yards
Answer: D
A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be
installed. How many cubic yards of concrete will be required?
A. 3.0 cubic yards
B. 2.0 cubic yards
C. 3.5 cubic yards
D. 2.5 cubic yards
Answer: D
Subscribe to:
Posts (Atom)