Question No 7:

A major theme park is expanding the existing facility over a five-year period. The design
phase will be completed one year after the contract is awarded. Major engineering
drawings will be finalized two years after the design contract is awarded and construction
will begin three years after the award of the design contract. New, unique ride technology
will be used and an estimate will need to be developed to identify these costs that have no
historical data.
The project scheduler left the company and has left unfinished work. You have been hired
as the new project scheduler and must update the existing schedule. What will be your first task?

A.
Recalculate the early finish for each activity
B.
Recalculate the early start for each activity
C.
Update the remaining duration for each activity
D.
Recalculate the critical path

Answer: D