Budgeted cost of work scheduled is all of the following except:

A.
Total costs incurred in accomplishing work in a given-time period
B.
Baseline for performance measurement
C.
Sum of the budgets for work scheduled
D.
Includes portion of the budget for level-of-effort work

Answer: D